System Commissioning
System Commissioning Instructions
Figure commissioning flow chart
|
System commissioning is a professional operation, and the following requirements must be observed before commissioning: Power-on &commissioning must be authorized by trained personnel. Ensure that aPower and aGate are installed completed firmly in the place before commissioning. Ensure that aPower stop bush is off and the aGate breakers are turned off position. Ensure that the system ground is installed. Ensure that the signal and power cables are connected correctly and firmly. |
Step 1: Install APP and register user account
Figure QR code for download FranklinWH APP
Download and install FranklinWH APP.
Channel I: Scan the QR code to download and install APP.
Channel II: Search FranklinWH in AppStore/ GooglePlay to download and install APP.
Figure User sign up interface
Help user register the account number, and then records the email account for future service.
Step 2: First Power-on
- Keep all breakers at the off positions.
- Push the aPower push button up to active the aPower unit one by one.
Step 3: Log in to the commissioning account
Figure UI of log in the commissioning account
Login commissioning account(Only for the commissioning use).
Enter App homepage, connect Wi-Fi hotspot from aGate named as “AP_” started and click "OK".
Step 4: Setting parameters
Figure UI of Setting parameters
Return to App main interface to obtain the units status information as above.
Figure UI of user common setting
Click the user common setting interface to configure latitude/longitude information and network information.
Figure UI of the first install for automatic addressing
Return to the main interface and click the icon of the first install, enter the automatic address interface, enter the number of addresses (not exceeding 15).
Figure UI of system parameter setting
Return the main UI and click enter the system parameter setting interface and set the parameters of electrical policy, resource policy, and battery policy.
Figure UI of On-grid compliance
Enter the on-grid compliance interface in the system parameters setting, set the parameters for on/off-grid connections according to local grid policy.
Figure UI of power electrical setting
Enter the parameter setting page in the system parameter settings and set the breakers capacity, PV capacity, and generator power configured by the customer.
Figure UI of BIND DEVICE
Enter the APP UI binding page to bind the user email accounts and equipment.
Figure Turn on grid breakers at aGate
- Turn on the grid breaker.
- Return the main UI
Figure UI of Device Settings
Enter UI of Device Settings, active the debug mode icon, set the charge and discharge settings, debug the unit charge and discharge functions.
Figure Solar active
Close PV input breaker and active the PV input. App back to main UI.
Step 5: Setting of system operating mode and smart circuit settings
Figure Back the UI of user login
Logout of the commissioning account and re-login the user account shown in step 1.
Figure view user main UI
Check the main UI after re-login successfully, go to the front page to view the information of previously bound units.
Figure UI of User Setting
Go to the settings page and set up the system work mode. Log out of the user account.
Figure UI of smart circuit settings
Go to the load control page to control the intelligent load branch ON/OFF (if optional). Please ignore it if not selected.
Commissioning completed